Fields
To create as much transparency as possible, all relevant fields are explained and described.
Specifies a factor in case of a production bom. This includes possibly scrap.
BOM Quantity = A * B * C
A = Quantity per
B = 1 + scrap % (from BOM) / 100
C = BOM Quantity (if Production BOM within Production BOM)
If working without Type = Production BOM then BOM Quantity = 1
In case of a work center or machine center BOM Quantity = 0
Specifies the quantity used to calculate purchase prices and expected operation cost amt.
Specifies the total cost of the the item or resource on the line.
a) In case of an item
Cost Amount (LCY) = Unit Cost (LCY) * Quantity
b) in case of work center or machine center
Cost Amount (LCY) = Expected Operation Cost Amt.
c) In the case of a module, the Cost Amount (LCY) is the sum of the “cost amounts (LCY)” of all related modules, items, work centers and machine centers.
Specifies the total cost of the the item or resource on the line.
a) In case of an item
Direct Cost Amount = Direct Unit Cost * Quantity
b) In case of work centers or machine centers
Direct Cost Amount = Expected Operation Cost Amt.
c) In the case of a module, the “Direct Cost Amount” is the sum of the “direct cost amounts” of all related moduls, items, work centers and machine centers.
Specifies the cost of one unit of the selected item or resource.
b) In case of work center group or work centers, the purchase price from the master data is used.
c) In the case of a module
Direct Unit Cost = Direct Cost Amount / Quantity
Specifies the sum of components/time required to produce the parent item.
a) In the case of an item or a module
Quantity = A * B * C * D * E * F + G
A = Quantity per
B = BOM Quantity
C = Quantity (of the module)
D = 1 + item scrap % (module) / 100
E = 1 + scrap % (component) / 100
F = 1+ Scrap Factor % (Accumulated) (routing)
G = Fixed Scrap Quantity (Accumulated) (routing)
b) In case of a work center or machine center
Quantity = A + B * (C * D * E +F)
A = Setup time
B = Run time
C = Quantity base (module)
D = 1 + Scrap Factor % (Accumulated)
E = 1 + Item scrap % (module) / 100
F = Fixed Scrap Quantity (Accumulated)